Subpart 1. General distance.
The minimum isolation distances in item A or B must be maintained during construction, repair, or sealing of a well or boring, and installation of a pipe with flammable or volatile gas, an overhead or underground electric transmission, distribution, service, supply, feeder, branch, or conductor line hereafter called "electric line" or "line," or a liquid propane tank. The distances are measured horizontally from the closest part of the well or boring to the closest part of the pipe, tank, or line; or closest part of the vertical projection on the earth of an overhead or buried pipe, tank, or line. The minimum isolation distance between a well or boring and a pipe with flammable or volatile gas, an electric line, or a liquid propane tank is:
Subp. 2. [Repealed, 33 SR 211]
Subp. 3. Exceptions.
Subpart 1 does not apply to:
The requirements of this part are minimum standards and do not exempt persons from more restrictive requirements of the Occupational Safety and Health Administration.
Statutory Authority: MS s 103I.101; 103I.111; 103I.205; 103I.221; 103I.301; 103I.401; 103I.451; 103I.501; 103I.525; 103I.531; 103I.535; 103I.541; 103I.621; 144.05; 144.12; 144.383; 157.04; 157.08; 157.09; 157.13