This part applies to an excavation or hole for installation of an elevator boring.
A. An elevator boring must not be constructed until a permit has been issued by the commissioner to the elevator boring contractor or well contractor.
B. An elevator boring contractor or well contractor must submit to the commissioner an elevator boring permit application on a form provided by the commissioner, or in a format approved by the commissioner. The application must be legible and signed by the elevator boring contractor or well contractor.
C. The permit must include the following information for each elevator boring:
D. Permit applications for elevator borings constructed through a confining layer must include the following information in addition to that required in item C:
E. The permit is valid for 18 months from the date issued.
Statutory Authority: MS s 103I.101; 103I.111; 103I.205; 103I.221; 103I.301; 103I.401; 103I.451; 103I.501; 103I.525; 103I.531; 103I.535; 103I.541; 103I.621; 144.05; 144.12; 144.122; 144.383; 157.04; 157.08; 157.09; 157.13