Part 4725.1833 - BORED GEOTHERMAL HEAT EXCHANGER CONSTRUCTION PERMITS
Current through Register Vol. 49, No. 13, September 23, 2024
This part applies to the construction of bored geothermal heat exchangers, including bored geothermal heat exchanger piping installed in a boring for thermal conductivity testing.
A. A bored geothermal heat exchanger must not be constructed, or have piping installed or removed below the frost line, until a permit has been issued by the commissioner to the well or bored geothermal heat exchanger contractor
B. The well contractor or bored geothermal heat exchanger contractor must submit to the commissioner a bored geothermal heat exchanger permit application on a form provided by the commissioner The application must be legible and signed by the well contractor or bored geothermal heat exchanger contractor and the property owner or property owner's agent. The application must include:
C. The well contractor or bored geothermal heat exchanger contractor must inform the commissioner of the proposed construction starting time 24 hours before starting construction of bored geothermal heat exchanger borings. The information must be reported by telephone, facsimile, electronically, or in person between 8:00 a.m. and 4:30 p.m., Monday through Friday, excluding holidays.
D. The vertical heat exchanger must be constructed within 18 months of the date the permit is issued.
Statutory Authority: MS s 103I.101; 103I.111; 103I.205; 103I.221; 103I.301; 103I.401; 103I.451; 103I.501; 103I.525; 103I.531; 103I.535; 103I.541; 103I.621; 144.05; 144.12; 144.122; 144.383; 157.04; 157.08; 157.09; 157.13