Minnesota Administrative Rules
Agency 144 - Health Department
Chapter 4720 - PUBLIC WATER SUPPLIES
PROCEDURES FOR WELLHEAD PROTECTION PLAN DEVELOPMENT AND REVIEW
Part 4720.5340 - SECOND SCOPING MEETING PROCEDURES
Current through Register Vol. 49, No. 13, September 23, 2024
Subpart 1. Scoping meeting; remaining portion of wellhead protection plan.
A public water supplier and the department shall meet to discuss the data elements specified in part 4720.5400 that the department determines must be contained in the wellhead protection plan and used to prepare the remaining portion of the wellhead protection plan.
Subp. 2. Scoping decision; notice.
No later than 30 days after the scoping meeting specified in subpart 1, the department shall notify the public water supplier in writing of the data elements specified in part 4720.5400 that must be:
Statutory Authority: MS s 103I.101