Minnesota Administrative Rules
Agency 144 - Health Department
Chapter 4720 - PUBLIC WATER SUPPLIES
PROCEDURES FOR WELLHEAD PROTECTION PLAN DEVELOPMENT AND REVIEW
Part 4720.5320 - AQUIFER TEST PLAN; PROCEDURES
Current through Register Vol. 49, No. 13, September 23, 2024
Subpart 1. Submittal.
An aquifer test plan as specified in part 4720.5540 must be submitted to the department by a public water supplier for department approval:
Subp. 2. Review; notice.
No later than 30 days after receipt of an aquifer test plan, the department shall:
Subp. 3. Disapproval notice.
If an aquifer test plan is disapproved, the department shall, as part of the notice of disapproval, provide the public water supplier with:
Subp. 4. Resubmittal.
A disapproved aquifer test plan must be revised by the public water supplier and resubmitted to the department within 45 days after receiving notice of disapproval.
Subp. 5. Revised aquifer test plan; review.
On receipt of a revised aquifer test plan, the department shall follow the same review process as for an original submittal.
Statutory Authority: MS s 103I.101