Part 4620.3560 - ASBESTOS PROJECT PLAN
Current through Register Vol. 49, No. 13, September 23, 2024
Subpart 1. Applicability.
For each project other than a project in a single-family residence executed by the domiciled owner of the residence, the person performing abatement must prepare a project-specific asbestos project plan.
Subp. 2. Plan availability.
The person performing abatement must have a complete and current asbestos project plan available for inspection at the project site at the start of the project.
Subp. 3. Asbestos project plan content.
The asbestos project plan must contain:
Subp. 4. Asbestos project plan changes.
If any information was estimated or a change occurs during the project, the new information must be added to the asbestos project plan as it becomes known.