Minnesota Administrative Rules
Agency 144 - Health Department
Chapter 4620 - CLEAN INDOOR AIR
ASBESTOS ABATEMENT
Part 4620.3415 - AMENDMENT OF NOTICE
Current through Register Vol. 49, No. 13, September 23, 2024
The licensed asbestos contractor performing abatement must notify the commissioner according to this part of any change in the information reported to the commissioner by that contractor under part 4620.3410.
A. All amendments except for work shift times and dates must be in writing with the permit number and the changes clearly indicated.
B. Any amendment of the project start date to an earlier start date must be received by the commissioner at least five calendar days before abatement begins.
C. An amendment, other than a change of the project start date to an earlier start date, must be received by the commissioner no later than the effective date and time of the change.
D. Any amendment of the dates or work shift times, other than the project start and end dates, must be received by the commissioner by voice mail, telephone, facsimile, mail, or delivery.
Statutory Authority: MS s 144.05; 326.70 to 326.81