Minnesota Administrative Rules
Agency 138 - Public Utilities Commission
Chapter 7855 - CERTIFICATE OF NEED; LARGE ENERGY FACILITY
APPLICATIONS FOR CERTIFICATE OF NEED
Part 7855.0240 - SCHEDULE OF OTHER FILINGS

Universal Citation: MN Rules 7855.0240

Current through Register Vol. 49, No. 13, September 23, 2024

Each application shall contain a schedule listing all known federal, state, and local agencies or authorities with which the applicant must file for the proposed facility. The following information shall be included on the schedule:

A. the names of all known federal, state, or local authorities with which the applicant must file;

B. the title of each required permit or certificate issued by the authorities named in response to item A and needed by the applicant;

C. for each permit or certificate listed in response to item B, the date an application was filed or the projected date of future application;

D. for each permit or certificate listed in response to item B, the actual date a decision was made on the application, or the anticipated decision date; and

E. for each permit or certificate listed in response to item B for which an application was filed, the disposition or status of the permit or certificate.

Statutory Authority: MS s 216B.08; 216B.2421; 216B.243; 216C.10

Disclaimer: These regulations may not be the most recent version. Minnesota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.