Subpart 1. Fees.

The fee for processing an application shall be:

A. $5,000 plus $50 per ton of hourly design input for a new or expanded fuel conversion facility;

B. $5,000 plus $10 per mton-mile for a new or expanded coal slurry pipeline;

C. $5,000 plus $1 per mbpd-mile for a new or expanded coal liquids pipeline;

D. $20,000 plus $50 per ton of yearly design input for a nuclear fuel processing facility; or

E. $20,000 for a nuclear waste storage or disposal facility; plus such additional fees as are reasonably necessary for completion of the evaluation of need for the proposed facility.

Subp. 2. Schedule.

Fifty percent of the fee set according to subpart 1, items A to D shall accompany the application and the balance shall be paid 90 days after submission of the application. The applicant shall be notified prior to the time the application is acted upon by the commission of any additional fees, which fees shall be paid within 30 days of notification. The billing of such additional fees shall be accompanied by an itemized document showing the necessity for the additional assessment.

Subp. 3. Payment required.

No certificate shall be issued until all fees are paid in full.

Statutory Authority: MS s 216B.08; 216B.2421; 216B.243; 216C.10

Disclaimer: These regulations may not be the most recent version. Minnesota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.