Minnesota Administrative Rules
Agency 138 - Public Utilities Commission
Chapter 7855 - CERTIFICATE OF NEED; LARGE ENERGY FACILITY
ADDITIONAL INFORMATION FOR NUCLEAR FUEL PROCESSING FACILITIES
Part 7855.0500 - PROPOSED NUCLEAR FUEL PROCESSING FACILITY; DESCRIPTION
Universal Citation: MN Rules 7855.0500
Current through Register Vol. 49, No. 27, December 30, 2024
Each application for a nuclear fuel processing facility shall contain the following information:
A. a physical description of the facility, including:
(1) its location, to the fullest
extent known;
(2) the required land
area, the height of the tallest structures, and, if applicable, the depth and
size of any underground caverns;
(3) its design capacity in tons per year of
input material; and
(4) a schematic
drawing showing major components of the facility;
B. data regarding design and construction of the facility, including:
(1) if known, the
complete name and business address of the engineer and firm that would be
responsible for the design of the facility;
(2) if known, the complete name and business
address of the company which would construct the facility;
(3) the proposed date for commencing
construction and the proposed in-service date;
(4) the estimated installed cost of the
facility in current dollars; and
(5) the estimated economic life of the
facility;
C. data regarding operation of the facility, including:
(1) a narrative description of the steps of
the process;
(2) the sources and
amounts of input materials that would be processed by the facility during
operation at the design capacity, including uranium, plutonium, and structural
metals in tons per year and fission product nuclides in curies per
year;
(3) the types and amounts of
output materials from the processing facility during operation at the design
capacity;
(4) the projected annual
operating and maintenance costs in current dollars for each of the first five
calendar years of operation;
(5)
the methods that would be used to transport materials to and from the
facility;
(6) the projected types
and amounts of energy products that would be consumed during operation at the
design capacity;
(7) the expected
average percentage of use of the full design capacity for each of the first
five calendar years of operation; and
(8) a discussion of the maintenance
requirements of the facility, including the estimated impact on
production.
Statutory Authority: MS s 216B.08; 216B.2421; 216B.243; 216C.10
Disclaimer: These regulations may not be the most recent version. Minnesota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.