Minnesota Administrative Rules
Agency 138 - Public Utilities Commission
Chapter 7855 - CERTIFICATE OF NEED; LARGE ENERGY FACILITY
ADDITIONAL INFORMATION FOR FUEL CONVERSION FACILITIES
Part 7855.0350 - WASTES AND EMISSIONS
Current through Register Vol. 49, No. 13, September 23, 2024
The applicant shall supply data on wastes and emissions associated with construction or operation of the facility, including:
A. the types and estimated amounts of solid and liquid wastes, including aromatic compounds, that would be produced by the facility;
B. the types and estimated amounts of gaseous and particulate emissions into the air that would occur during full operation from each emission source, and the location and nature of the release point;
C. locations that may be sources of fugitive dust and the nature of each source;
D. the locations, routes, and final receiving waters for any discharge points, and for each discharge point the source, the amount, and the nature of the discharge;
E. any area from which runoff may occur, potential sources of contamination in the area, and receiving waters for any runoff;
F. the sources and estimated amounts of heat rejected from the facility; and
G. the maximum noise levels (in decibels, A scale) expected at the property boundary and the expected maximum increase over ambient noise levels.
Statutory Authority: MS s 216B.08; 216B.2421; 216B.243; 216C.10