Chapter 7854 - SITE PERMIT; LARGE WIND ENERGY SYSTEM
Part 7854.1100 - PERMIT AUTHORITY LIMITED

Universal Citation: MN Rules 7854.1100

Current through Register Vol. 49, No. 27, December 30, 2024

Subpart 1. Wind rights.

Nothing in a site permit for an LWECS shall be construed to convey the right to install a wind turbine in an area within the boundaries of the project for which the permittee does not hold the wind rights.

Subp. 2. Other LWECS construction.

Nothing in a site permit for an LWECS shall be construed to preclude another person from seeking a site permit to construct an LWECS in an area within the boundaries of the project covered by the permit if the permittee does not hold exclusive wind rights for the areas.

Subp. 3. Power purchase agreement.

A site permit does not authorize construction of the project until the permittee has obtained a power purchase agreement or some other enforceable mechanism for sale of the power to be generated by the project. If the permittee does not have a power purchase agreement or other enforceable mechanism at the time the permit is issued, the commission shall provide in the permit that the permittee shall advise the commission when it obtains a commitment for purchase of the power. The commission may establish as a condition in the permit a date by which the permittee must obtain a power purchase agreement or other enforceable mechanism or the site permit is null and void.

Statutory Authority: MS s 116C.695; 216F.05

Disclaimer: These regulations may not be the most recent version. Minnesota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.