Subpart 1. Preliminary determination.

Within 45 days after acceptance of the application by the commission, the commission shall make a preliminary determination whether a permit may be issued or should be denied. If the preliminary determination is to issue a permit, the commission shall prepare a draft site permit for the project. The draft site permit must identify the person or persons who will be the permittee, describe the proposed LWECS, and include proposed permit conditions.

Subp. 2. Effect of draft site permit.

A draft site permit does not authorize a person to construct an LWECS. The commission may change the draft site permit in any respect before final issuance or may deny the site permit.

Statutory Authority: MS s 116C.695; 216F.05

Disclaimer: These regulations may not be the most recent version. Minnesota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.