Minnesota Administrative Rules
Agency 138 - Public Utilities Commission
Chapter 7853 - CERTIFICATE OF NEED; PETROLEUM FACILITY
APPLICATIONS FOR CERTIFICATES OF NEED
Part 7853.0210 - FILING FEES AND PAYMENT SCHEDULE

Universal Citation: MN Rules 7853.0210

Current through Register Vol. 49, No. 13, September 23, 2024

Subpart 1. Fees.

The fee for processing an application shall be:

A. $2,000 plus $10 per 100,000 gallons of design storage capacity for a large LPG storage facility; or

B. $5,000 plus $1 for each mbpd-mile for a large petroleum pipeline;

plus such additional fees as are reasonably necessary for completion of the evaluation of need for the proposed facility.

In no event shall the total fee required of any applicant exceed $50,000.

Subp. 2. Schedule.

Fifty percent of the fee set according to subpart 1 shall accompany the application, and the balance shall be paid 90 days after submission of the application. The applicant shall be notified when any additional fees are due and shall pay them within 30 days of notification. The billing for such additional fees shall be accompanied by an itemized statement.

Subp. 3. Payment required.

No certificate of need shall be issued unless all fees are paid in full.

Statutory Authority: MS s 16A.1283; 216B.08; 216B.243; 216C.10

Disclaimer: These regulations may not be the most recent version. Minnesota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.