Minnesota Administrative Rules
Agency 138 - Public Utilities Commission
Chapter 7852 - ROUTE PERMIT; PIPELINE
PIPELINE ROUTING PERMIT
Part 7852.3500 - RIGHT-OF-WAY PLAN AND PROFILE CONSTRUCTION SPECIFICATIONS REVIEW
Following issuance of a pipeline routing permit, a permittee shall provide the commission with a plan and profile of the right-of-way and the specifications and drawings for right-of-way preparation, construction, and restoration at least 14 days before right-of-way preparation of that segment of the pipeline. The commission may shorten this time limit if it can be shown that earlier construction will not preclude proper review. If the permittee makes any significant change in its plan and profile and the specifications and drawings for right-of-way preparation, construction, and restoration, it shall notify the commission in writing of the changes.
Statutory Authority: MS s 116I.015; 216G.02