Minnesota Administrative Rules
Agency 138 - Public Utilities Commission
Chapter 7852 - ROUTE PERMIT; PIPELINE
PIPELINE ROUTING PERMIT
Part 7852.3400 - PERMIT AMENDMENTS
Current through Register Vol. 49, No. 13, September 23, 2024
Following issuance of a pipeline routing permit, the permittee may apply to the commission for amendments on route location and conditions specified in the permit. The permittee shall submit an application for amendment that contains sufficient information for the commission to determine the following:
A. whether, in light of the criteria in parts 7852.0700 and 7852.1900, the requested changes are significant enough to warrant commission study and approval;
B. whether to order public information meetings near the affected area; and
C. whether additional fees shall be assessed.
The commission shall make the determinations in items A to C within 45 days of receipt of the application.
If the commission cannot make the determinations in items A to C in 45 days and decides to study the application further, the commission shall make the determinations in items A to C within 70 days. The commission shall grant or deny the permittee's application for permit amendment, as appropriate.
Statutory Authority: MS s 116I.015; 216G.02