Chapter 7852 - ROUTE PERMIT; PIPELINE
PIPELINE ROUTING PERMIT
Part 7852.3300 - DELAY IN ROUTE CONSTRUCTION

Universal Citation: MN Rules 7852.3300
Current through Register Vol. 49, No. 13, September 23, 2024

When the commission issues a pipeline routing permit, the permittee may begin construction or improvement of the route in accordance with the conditions of the permit and this chapter. However, if construction and improvement have not begun within four years after the pipeline routing permit has been issued by the commission, the commission shall suspend the permit. If at that time, or at a later time after suspension, the permittee decides to construct the proposed pipeline, it shall certify to the commission that there have been no significant changes in any material aspects of the conditions or circumstances existing when the permit was issued. If the commission determines that there are no significant changes, it shall reinstate the permit. If the commission determines that there is a significant change, it may order public information meetings or a new hearing and consider the matter further, or it may require the permittee to submit a new application.

Statutory Authority: MS s 116I.015; 216G.02

Disclaimer: These regulations may not be the most recent version. Minnesota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.