Minnesota Administrative Rules
Agency 138 - Public Utilities Commission
Chapter 7852 - ROUTE PERMIT; PIPELINE
PIPELINE ROUTE SELECTION PROCEDURES
Part 7852.1500 - ALTERNATIVE ROUTE ANALYSIS
Universal Citation: MN Rules 7852.1500
Current through Register Vol. 49, No. 13, September 23, 2024
A comparative environmental analysis of all of the pipeline routes accepted for consideration at public hearings shall be prepared by the commission staff or by the applicant and reviewed by the commission staff. This comparative environmental analysis must be submitted as prefiled testimony as required by part 1405.1900.
Statutory Authority: MS s 116I.015; 216G.02
Disclaimer: These regulations may not be the most recent version. Minnesota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.