PIPELINE ROUTE SELECTION PROCEDURES
Part 7852.0900 - APPLICATION ACCEPTANCE NOTICE

Universal Citation: MN Rules 7852.0900

Current through Register Vol. 49, No. 13, September 23, 2024

Within 20 days of commission acceptance of an application for a pipeline routing permit under part 7852.2000, subpart 4, the commission shall provide published notice of acceptance of the application in a newspaper in each county in which a route is proposed by the applicant.

The notice must include:

A. identification of the applicant;

B. the date of the commission's acceptance of the application;

C. a brief description of the proposed facility including but not limited to size and type;

D. a map showing the routes proposed in that county;

E. the name and function of the public adviser and the address and telephone number where that person can be reached;

F. locations where the pipeline routing permit application is available to the public;

G. procedures for proposing alternate routes; and

H. notice of public information meetings.

Statutory Authority: MS s 116I.015; 216G.02

Disclaimer: These regulations may not be the most recent version. Minnesota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.