Minnesota Administrative Rules
Agency 138 - Public Utilities Commission
Chapter 7852 - ROUTE PERMIT; PIPELINE
PIPELINE ROUTE SELECTION PROCEDURES
Part 7852.0900 - APPLICATION ACCEPTANCE NOTICE
Current through Register Vol. 49, No. 13, September 23, 2024
Within 20 days of commission acceptance of an application for a pipeline routing permit under part 7852.2000, subpart 4, the commission shall provide published notice of acceptance of the application in a newspaper in each county in which a route is proposed by the applicant.
The notice must include:
A. identification of the applicant;
B. the date of the commission's acceptance of the application;
C. a brief description of the proposed facility including but not limited to size and type;
D. a map showing the routes proposed in that county;
E. the name and function of the public adviser and the address and telephone number where that person can be reached;
F. locations where the pipeline routing permit application is available to the public;
G. procedures for proposing alternate routes; and
H. notice of public information meetings.
Statutory Authority: MS s 116I.015; 216G.02