Minnesota Administrative Rules
Agency 138 - Public Utilities Commission
Chapter 7852 - ROUTE PERMIT; PIPELINE
EMERGENCY PROCEDURES
Part 7852.0400 - PIPELINE EMERGENCY ACTION AND PROCEDURES
Current through Register Vol. 49, No. 13, September 23, 2024
Subpart 1. Pipeline emergency action.
In the rare situation where immediate action by a pipeline company whose pipeline system requires the immediate construction of a pipeline is considered essential to avoid or eliminate an imminent threat, prevent injury, loss of life, property damage, or loss of essential public services, a pipeline project may be undertaken without the review that would otherwise be required by this chapter.
Subp. 2. Pipeline emergency procedures.
The pipeline company shall notify and demonstrate to the commission, either orally or in writing, that immediate action is essential and must receive temporary authorization from the commission to proceed. All oral requests must be followed by a written request within three working days. Temporary authorization to proceed must be determined by the commission as soon as possible after the request is made and must be limited to only those aspects of the project necessary to control the immediate impacts of the emergency.
Statutory Authority: MS s 116I.015; 216G.02