For the proposed pipeline, the applicant shall provide the following information:
A. permanent right-of-way length, average width, and estimated acreage;
B. temporary right-of-way (workspace) length, estimated width, and estimated acreage;
C. estimated range of minimum trench or ditch dimensions including bottom width, top width, depth, and cubic yards of dirt excavated;
D. minimum depth of cover for state and federal requirements; and
E. rights-of-way sharing or paralleling: type of facility in the right-of-way, and the estimated length, width, and acreage of the right-of-way.
Statutory Authority: MS s 116I.015; 216G.02