Minnesota Administrative Rules
Agency 138 - Public Utilities Commission
Chapter 7852 - ROUTE PERMIT; PIPELINE
APPLICATION CONTENTS
Part 7852.2100 - GENERAL INFORMATION
Current through Register Vol. 49, No. 13, September 23, 2024
Subpart 1. Cover letter.
Each application must be accompanied by a cover letter signed by an authorized representative or agent of the applicant. The cover letter must specify the type, size, and general characteristics of the pipeline for which an application is submitted.
Subp. 2. Title page and table of contents.
Each application must contain a title page and a complete table of contents.
Subp. 3. Statement of ownership.
Each application must include a statement of proposed ownership of the pipeline as of the day of filing and an affidavit authorizing the applicant to act on behalf of those planning to participate in the pipeline project.
Subp. 4. Background information.
Each application must contain the following information:
Statutory Authority: MS s 116I.015; 216G.02