Minnesota Administrative Rules
Agency 138 - Public Utilities Commission
Chapter 7851 - CERTIFICATE OF NEED; GAS STORAGE, PIPELINE
APPLICATIONS FOR CERTIFICATES OF NEED
Part 7851.0370 - INDUCED DEVELOPMENTS

Universal Citation: MN Rules 7851.0370

Current through Register Vol. 49, No. 13, September 23, 2024

Subpart 1. Vehicular traffic.

Estimate the amounts and types of vehicular traffic that would be generated by the facility due to construction activity and, later, operational needs.

Subp. 2. Water use.

Indicate the amount of water that would be appropriated and the amount that would be consumed by the facility, the expected source of the water, and how the water would be used.

Subp. 3. Agriculture.

Estimate the amount of land, including pasture land, that would be removed from agricultural use if the facility were constructed. Indicate known circumstances with regard to the facility that could lead to reduced productivity of agricultural land on or near the site or along the route. Estimate the amount of excavation, backfilling, grading, soil compaction and soil mixture, and ditching to be done in farm fields.

Subp. 4. Relocation of persons.

Estimate the number of people that would have to relocate if the facility were constructed.

Statutory Authority: MS s 216B.08; 216B.2421; 216B.243; 216C.10

Disclaimer: These regulations may not be the most recent version. Minnesota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.