Subpart 1. Vehicular traffic.
Estimate the amounts and types of vehicular traffic that would be generated by the facility due to construction activity and, later, operational needs.
Subp. 2. Water use.
Indicate the amount of water that would be appropriated and the amount that would be consumed by the facility, the expected source of the water, and how the water would be used.
Subp. 3. Agriculture.
Estimate the amount of land, including pasture land, that would be removed from agricultural use if the facility were constructed. Indicate known circumstances with regard to the facility that could lead to reduced productivity of agricultural land on or near the site or along the route. Estimate the amount of excavation, backfilling, grading, soil compaction and soil mixture, and ditching to be done in farm fields.
Subp. 4. Relocation of persons.
Estimate the number of people that would have to relocate if the facility were constructed.