Chapter 7850 - SITE OR ROUTE PERMIT; POWER PLANT OR LINE
Part 7850.5200 - EMERGENCY PERMIT
Current through Register Vol. 49, No. 13, September 23, 2024
Subpart 1. Application for emergency permit.
Any utility whose electric power system requires the immediate construction of a large electric power generating plant or high voltage transmission line due to a major unforeseen event may apply to the commission for an emergency permit. The application must contain the following information:
Subp. 2. Public hearing.
The PUC shall hold a public hearing on the application for an emergency permit. The hearing must be held within 90 days after the application is submitted. The hearing must be held in accordance with part 7850.3800.
Subp. 3. Final decision.
The commission shall make a final decision on an emergency permit within 195 days after the commission's acceptance of the application. The board shall grant the emergency permit if it finds the following:
Subp. 4. Permit conditions.
The commission may impose reasonable conditions in an emergency permit.
Subp. 5. Permit fee.
The applicant for an emergency permit shall pay the same fee as would be required for a regular permit for the same project.
Statutory Authority: MS s 116C.66; 216E.16