Minnesota Administrative Rules
Agency 138 - Public Utilities Commission
Chapter 7850 - SITE OR ROUTE PERMIT; POWER PLANT OR LINE
Part 7850.5000 - PERMIT TRANSFER
Current through Register Vol. 49, No. 13, September 23, 2024
Subpart 1. Application.
A permittee holding a large electric power generating plant site permit or a high voltage transmission line route permit may request the PUC to transfer its permit. The permittee shall provide the name of the existing permittee, the name and description of the entity to which the permit is to be transferred, the reasons for the transfer, a description of the facilities affected, and the proposed effective date of the transfer. The person to whom the permit is to be transferred shall provide the PUC with such information as the PUC shall require to determine whether the new permittee can comply with the conditions of the permit. The commission shall mail notice of receipt of the application to those persons on the general list at least seven days in advance of the commission's consideration of the matter. The commission shall provide the same notice to persons on the project contact list if such a list exists.
Subp. 2. Approval of transfer.
The commission shall approve the transfer if the commission determines that the new permittee will comply with the conditions of the permit. The commission, in approving the transfer of a permit, may impose reasonable additional conditions in the permit as part of the approval. The commission may decide to hold a public meeting to provide the public with an opportunity to comment on the request for the transfer prior to making a decision.
Statutory Authority: MS s 116C.66; 216E.16