Minnesota Administrative Rules
Agency 138 - Public Utilities Commission
Chapter 7850 - SITE OR ROUTE PERMIT; POWER PLANT OR LINE
Part 7850.4700 - DELAY IN ROUTE OR SITE CONSTRUCTION

Universal Citation: MN Rules 7850.4700
Current through Register Vol. 49, No. 13, September 23, 2024

If construction and improvement of a route or site have not commenced four years after the permit has been issued by the commission, the commission shall suspend the permit. If at that time, or at a time subsequent, the permittee decides to construct the proposed large electric power generating facility or high voltage transmission line, the permittee shall certify to the commission that there have been no significant changes in any material aspects of the conditions or circumstances existing when the permit was issued. The commission shall mail notice of receipt of the certification request to those persons on the general list at least seven days before the commission's consideration of the matter, and the same notice to those persons on the project contact list if such a list exists. If the commission determines that there are no significant changes, it shall reinstate the permit. If the commission determines that there is a significant change, it may order a new hearing and consider the matter further, or it may require the permittee to file a new application.

Statutory Authority: MS s 116C.66; 216E.16

Disclaimer: These regulations may not be the most recent version. Minnesota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.