Minnesota Administrative Rules
Agency 138 - Public Utilities Commission
Chapter 7850 - SITE OR ROUTE PERMIT; POWER PLANT OR LINE
Part 7850.4600 - PERMIT CONDITIONS

Universal Citation: MN Rules 7850.4600

Current through Register Vol. 48, No. 39, March 25, 2024

Subpart 1. Generally.

The commission shall impose in any site permit for a large electric power generating plant or route permit for a high voltage transmission line such conditions as the commission deems appropriate and are supported by the record.

Subp. 2. HVTL permits.

When the commission issues a permit for a route for a high voltage transmission line, the commission shall specify the design, route, right-of-way preparation, and facility construction and operation it deems necessary. The commission may impose a condition in the permit requiring the permittee to construct a high voltage transmission line that is capable of expansion in transmission capacity through multiple circuiting or design modifications.

Statutory Authority: MS s 116C.66; 216E.16

Disclaimer: These regulations may not be the most recent version. Minnesota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.