Minnesota Administrative Rules
Agency 138 - Public Utilities Commission
Chapter 7850 - SITE OR ROUTE PERMIT; POWER PLANT OR LINE
Part 7850.2800 - ELIGIBLE PROJECTS
Current through Register Vol. 49, No. 13, September 23, 2024
Subpart 1. Eligible projects.
An applicant for a site permit or a route permit for one of the following projects may elect to follow the procedures of parts 7850.2800 to 7850.3900 instead of the full permitting procedures in parts 7850.1700 to 7850.2700:
Subp. 2. Notice to PUC.
An applicant for a permit for one of the qualifying projects in subpart 1, who intends to follow the procedures of parts 7850.2800 to 7850.3700, shall notify the PUC of such intent, in writing, at least ten days before submitting an application for the project.
Statutory Authority: MS s 116C.66; 216E.16