Part 7850.2600 - CONTESTED CASE HEARING

Universal Citation: MN Rules 7850.2600

Current through Register Vol. 48, No. 39, March 25, 2024

Subpart 1. Hearing.

The PUC shall hold a contested case hearing after the draft environmental impact statement is prepared on all applications for a site permit or a route permit. The hearing must be conducted by an administrative law judge from the Office of Administrative Hearings pursuant to the contested case procedures of Minnesota Statutes, chapter 14. Notice of the hearing must be given in accordance with Minnesota Statutes, section 216E.03, subdivision 6. At least a portion of the hearing must be held in a county where the proposed large electric power generating plant or high voltage transmission line would be located.

Subp. 2. Issues.

Once the commission has determined questions of need, including size, type, and timing; questions of system configuration; and questions of voltage, those issues must not be addressed in the contested case hearing.

Subp. 3. Hearing.

If the commission determines that a hearing to consider both permitting and need issues is feasible, more efficient, and may further the public interest, the commission may decide to hold a hearing. The commission may also elect to hold a joint hearing with other states pursuant to Minnesota Statutes, section 216E.02, subdivision 3.

Statutory Authority: MS s 116C.66; 216E.16

Disclaimer: These regulations may not be the most recent version. Minnesota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.