Minnesota Administrative Rules
Agency 138 - Public Utilities Commission
Chapter 7850 - SITE OR ROUTE PERMIT; POWER PLANT OR LINE
Part 7850.1700 - PERMIT APPLICATION UNDER FULL PERMITTING PROCESS

Universal Citation: MN Rules 7850.1700

Current through Register Vol. 49, No. 13, September 23, 2024

Subpart 1. Filing of application for permit.

A person seeking a site permit or route permit for a large electric power generating facility must file three copies of the application for the permit with the PUC. Upon acceptance of the application, the commission will advise the applicant of how many copies of the application must be submitted to the PUC.

Subp. 2. Electronic copy.

A person filing an application for a site permit or route permit shall provide the PUC with an electronic version of the application suitable for posting on the PUC's Web page.

Statutory Authority: MS s 116C.66; 216E.16

Disclaimer: These regulations may not be the most recent version. Minnesota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.