FILING REQUIREMENTS
Part 7835.0300 - FILING DATES

Universal Citation: MN Rules 7835.0300
Current through Register Vol. 49, No. 13, September 23, 2024

Within 60 days after the effective date of this chapter, on January 1, 1985, and every 12 months thereafter, each utility must file with the commission, for its review and approval, a cogeneration and small power production tariff. The tariff for generating utilities must contain schedules A to G, except that generating utilities with less than 500,000,000 kilowatt-hour sales in the calendar year preceding the filing may substitute their retail rate schedules for schedules A and B. The tariff for nongenerating utilities must contain schedules C, D, E, F, and H, and may, at the option of the utility, contain schedules A and B, using data from the utility's wholesale supplier.

Statutory Authority: MS s 216A.05; 216B.08; 216B.164

Disclaimer: These regulations may not be the most recent version. Minnesota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.