Minnesota Administrative Rules
Agency 120 - Commerce Department
Chapter 7690 - ENERGY CONSERVATION IMPROVEMENT
Part 7690.1440 - TIMELINES FOR DIFFERENT PROGRAM FILINGS

Universal Citation: MN Rules 7690.1440

Current through Register Vol. 49, No. 13, September 23, 2024

Subpart 1. Generally.

Parts 7690.0500 to 7690.1430 specify the process for the submission, review and approval, modification, or disapproval of various conservation improvement program filings. To both facilitate understanding and to serve as a reference guide, the timelines for completing the review and approval process of the various filings is summarized in subparts 2 to 4. See parts 7690.0500 to 7690.1430 for specific review and approval process requirements.

Subp. 2. Biennial program filings.

The timelines for biennial conservation improvement program (CIP) filings are summarized in this subpart. See parts 7690.0500 to 7690.1430 for specific review and approval process requirements.

ACTION DUE DATE
Filing of biennial plan August 1, odd-numbered years for electric utilities July 1, even-numbered years for gas utilities
Notice of completion 10 calendar days after biennial CIP filing is filed with department
Comments on filing 30 calendar days after notice of completion is issued
Reply comments 15 calendar days after comments are filed with department
Proposed decision 30 calendar days after reply comments are due
Written comments 15 calendar days after proposed decision is issued
Commissioner decision 30 calendar days after written comments on proposed decision are due

Subp. 3. New project proposals; terminating existing projects.

The timelines for a new project proposal and for terminating an existing project are summarized in this subpart. See parts 7690.0500 to 7690.1430 for specific review and approval process requirements.

ACTION DUE DATE
Filing of proposal Anytime
Notice of completion 10 calendar days after proposal is filed with department
Written comments 15 calendar days after notice of completion is issued
Reply comments 15 calendar days after written comments are filed with department
Proposed decision 10 calendar days after reply comments are due
Written comments 15 calendar days after proposed decision is issued
Commissioner decision 30 calendar days after comments on proposed decision are due

Subp. 4. Modifying or expanding existing project.

The timelines for modifying or expanding an existing project are summarized in this subpart. See parts 7690.0500 to 7690.1430 for specific review and approval process requirements.

ACTION DUE DATE
Filing of proposal Anytime
Written comments 15 calendar days after proposal is filed with department
Reply comments 10 calendar days after written comments are filed with department
Commissioner decision 35 days after reply comments are due

Statutory Authority: MS s 216B.241

Disclaimer: These regulations may not be the most recent version. Minnesota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.