For the following tasks, the cost is prima facie unreasonable when it exceeds the amount specified for it in the bid for contractor services or the maximum cost specified when the task was started, whichever is less:
A. clean fill purchase, transportation, and installation has a maximum cost of $19 per cubic yard;
B. drum disposal has a maximum cost of $182 for a drum and its contents plus $79 per hour for the associated loading and hauling;
C. excavation has a maximum cost of $9 per cubic yard;
D. hauling has a maximum cost of $121 plus $0.30 per cubic yard/mile;
E. loading has a maximum cost of $3.63 per cubic yard;
F. pumping of free product or petroleum-contaminated water using a vacuum truck has a maximum cost of:
G. soil test pit excavation has a maximum cost of $121 per test pit;
H. stockpiling has a maximum cost of:
I. surface disposal tipping fees has a maximum cost of the reasonable actual cost charged by the disposal facility;
J. treatment of free product or petroleum-contaminated water has a maximum cost of:
K. utility clearance has a maximum cost of:
Statutory Authority: MS s 115C.07