Michigan Administrative Code
Department - Licensing and Regulatory Affairs
Public Service Commission
Underground Electric Lines
Section R. 460.514 - Costs in case of special conditions
Universal Citation: MI Admin Code R. 460.514
Current through Vol. 24-16, September 15, 2024
Rule 4. Where practical difficulties exist, such as frost or water conditions, rock near the surface, or where there are requirements for deviation from the utility's filed construction standards, the per foot charges in R 460.512 and R 460.513 will not apply, and the contribution in aid of construction will be equal to the estimated difference in cost between overhead and underground facilities but not less than the charge calculated under R 460.512 and R 460.513.
Disclaimer: These regulations may not be the most recent version. Michigan may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.