Michigan Administrative Code
Department - Licensing and Regulatory Affairs
Public Service Commission
Underground Electric Lines
Section R. 460.511 - Payment of difference in costs

Universal Citation: MI Admin Code R. 460.511
Current through Vol. 24-04, March 15, 2024

Rule 1. In the case of all underground extensions of electric distribution facilities as covered by these rules, the real estate developer or customer shall make a contribution in aid of construction to the utility in an amount equal to the estimated difference in cost between overhead and underground facilities. "Distribution facilities" means those operated at 15,000 volts or less to ground for ___ connected systems and 20,000 volts or less for delta connected systems.

For the effective dates of R 460.511 and R 460.514 to R 460.519, see R 460.519.

Disclaimer: These regulations may not be the most recent version. Michigan may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.