Rule 14.
(1) A facility owner or facility operator shall do all of the following:
(a) Become and remain a member of the
notification system as required under section 4(1) of the act, MCL
460.724(1).
(b) Participate in and pay the fees levied by
the notification system as required under section 4(4) of the act, MCL
460.724(4).
(c) Respond to a ticket by the start date and
time of the excavation or blasting as required under section 7(1) of the act,
MCL
460.727(1).
(d) Provide notification to the notification
system using positive response as required under section 7(3) of the act, MCL
460.727(3).
(e) Mark facilities in accordance with the
uniform color code as required under section 7(2) of the act, MCL
460.727(2),
without charging a fee as required under section 4(3) of the act, MCL
460.724(3).
(f) Mark a facility within 24 hours, not
including hours on nonbusiness days, of receiving a notification from an
excavator that previous marks have been covered or destroyed as required under
section 7(4) of the act, MCL
460.727(4).
(g) Provide additional assistance if
necessary as required under section 7(5) of the act, MCL
460.727(5).
(h) Respond to a damage notice or emergency
notice as required under section 7(6) and (7) of the act, MCL
460.727(6)
and (7).
(i) Construct new facilities after April 1,
2014 in a manner that allows their detection as required under section 7(8) of
the act, MCL
460.727(8).
(2) An excavator shall do all of the following:
(a) Provide a dig notice to
the notification system as required under section 5(1) and (2) of the act, MCL
460.725(1)
and (2).
(b) Expose all facilities prior to blasting
or excavating as required under section 5(5) of the act, MCL
460.725(5).
(c) Support or brace facilities as required
under section 5(6) of the act, MCL
460.725(6).
(d) Provide notice, immediate additional
notice, or emergency notice if necessary as required under section 5(7) to (12)
of the act, MCL
460.725(7)
to (12)
(e) Take reasonable protective measures in
the event of facility damage as required under section 5(11) of the act, MCL
460.725(11).
(f) Provide white lining if necessary in
advance of submitting a ticket to a facility owner or facility operator as
required under section 5(13) of the act, MCL
460.725(13).
Disclaimer: These regulations may not be the most recent version. Michigan may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.