Section R. 460.964 - Interconnection agreement
Current through Vol. 24-16, September 15, 2024
Rule 64.
(1) For level 1, 2, or 3 interconnection applications, where no construction of interconnection facilities or distribution upgrades is required, an electric utility shall transmit its standard level 1, 2, and 3 interconnection agreement, which may include modifications to address any special operating conditions, to an applicant within 3 business days of reaching this stage.
(2) For level 1, 2, or 3 interconnection applications, where construction of interconnection facilities or distribution upgrades is required, an electric utility shall provide its standard level 1, 2, and 3 interconnection agreement with modifications to address any special operating conditions, required construction activities, estimated construction milestone timing, and estimated cost to an applicant within 5 business days of reaching this stage. The applicant and electric utility shall mutually agree on the timing of construction milestones.
(3) For an applicant with level 1, 2, or 3 interconnection applications, the applicant shall sign and return the standard level 1, 2, and 3 interconnection agreement with payment, if applicable, within 20 business days of receiving the agreement.
(4) For level 1, 2, or 3 projects, the electric utility shall countersign and provide a completed copy of the standard level 1, 2, and 3 interconnection agreement within 10 business days of the applicant returning the signed standard level 1, 2, and 3 interconnection agreement and the interconnection application must proceed under R 460.966.
(5) For level 4 or 5 projects, the electric utility shall provide its level 4 and 5 interconnection agreement, which may include modifications to address any special operating conditions, within 15 business days of reaching this stage. When construction of interconnection facilities or distribution upgrades is necessary, the level 4 and 5 interconnection agreement must contain either estimated timelines for completion of activities and estimates of construction costs or a timetable when these requirements can be determined. The interconnection agreement must include a payment schedule that corresponds to the milestones established and must require the electric utility to refund any unspent and unobligated funds if the agreement is terminated.
(6) For an applicant with level 4 or 5 DERs, the applicant shall sign and return with payment, if applicable, a level 4 and 5 interconnection agreement within 30 business days.
(7) For level 4 or 5 projects, an electric utility shall countersign and provide a completed copy of the level 4 and 5 interconnection agreement within 10 business days of the applicant returning a mutually agreed-upon and signed level 4 and 5 interconnection agreement and the interconnection application must proceed under R 460.966.
(8) An applicant shall pay the actual cost of the interconnection facilities and distribution upgrades. The cost to the applicant for interconnection facilities and distribution upgrades may not exceed 110% of the estimate without an itemized summary and explanation of cost increases being provided to the applicant. If the costs are expected to exceed 125% of the estimate, the electric utility shall provide further explanation to the applicant prior to the costs being incurred. If the applicant does not consent in writing to pay the additional costs within 20 business days after receiving further explanation from the electric utility, the electric utility shall initiate informal mediation pursuant to R 460.904 no later than 5 business days after the conclusion of the 20-business day applicant consent period. The applicant may dispute the expected costs pursuant to either informal mediation pursuant to R 460.904, formal mediation pursuant to R 460.906, or the complaint process pursuant to R 792.10439 to R 792.10446. If there is a dispute, the applicant shall make payment within 30 business days after final resolution of the dispute.
(9) A party's obligations under the interconnection agreement may be extended by agreement. If a party anticipates that it will be unable to meet a milestone for any reason other than an unforeseen event, the party shall do all of the following:
(10) The party affected by the failure to meet a milestone shall not withhold agreement to any amendments proposed in subrule (9)(c) of this rule unless 1 of the following applies:
(11) If the party affected by the failure to meet a milestone disputes the proposed extension, the affected party may pursue either informal mediation pursuant to R 460.904, formal mediation pursuant to R 460.906, or the complaint process pursuant to R 792.10439 to R 792.10446.
(12) The electric utility shall provide the applicant with a final accounting report of any difference between costs charged to the applicant and previous payments to the electric utility for interconnection facilities or distribution upgrades. Both of the following apply to a final accounting:
(13) The electric utility is responsible for specifying requirements in interconnection agreements to support independent system operator regulations or regional transmission operator regulations.
(14) The electric utility may propose to the commission that a signed interconnection agreement be modified to require compliance with changes to an independent system operator, a regional transmission operator, or the state's regulations. Unless the electric utility has the consent of the applicant or interconnection customer in writing, an electric utility shall not modify a signed interconnection agreement without commission approval.