Michigan Administrative Code
Department - Licensing and Regulatory Affairs
Public Service Commission
Interconnection and Distributed Generation Standards
Part 2 - INTERCONNECTION STANDARDS
Section R. 460.958 - Scoping meeting for interconnection applications that are to be studied individually
Current through Vol. 24-16, September 15, 2024
Rule 58.
(1) This rule applies only to interconnection applications proceeding pursuant to an individual study agreement.
(2) Upon request of the applicant, the electric utility and the applicant shall schedule a scoping meeting between the electric utility and the applicant to discuss the interconnection application and review existing fast track results, if any. The scoping meeting must take place within 20 business days after the interconnection application is considered complete by the electric utility or, if applicable, the fast track has been completed and the applicant has elected to continue with the system impact study or facilities study.
(3) Scoping meetings are limited to 1 hour per application. Multiple applications by the same applicant may be addressed in the same meeting.
(4) The scoping meeting may occur in-person or via telecommunications.
(5) During the scoping meeting, the electric utility shall identify and communicate to the applicant whether the applicant must proceed to a system impact study, a facilities study, or an interconnection agreement and the basis for that decision, and 1 of the following must occur: