Part 2 - INTERCONNECTION STANDARDS
Section R. 460.956 - Alternative process
Universal Citation: MI Admin Code R. 460.956
Current through Vol. 24-16, September 15, 2024
Rule 56. An electric utility may use a process to study interconnection applications that is different from the process described by R 460.954 and R 460.958 to R 460.962. If an electric utility elects to use an alternative process, this process must be described in the electric utility's interconnection procedures.
Disclaimer: These regulations may not be the most recent version. Michigan may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.