Michigan Administrative Code
Department - Licensing and Regulatory Affairs
Public Service Commission
Interconnection and Distributed Generation Standards
Part 2 - INTERCONNECTION STANDARDS
Section R. 460.952 - Study track
Current through Vol. 24-22, December 15, 2024
Rule 52.
(1) An electric utility shall use the study track to evaluate an interconnection application that has been accepted under R 460.936 if 1 or more of the following conditions is met:
(2) If the interconnection application must be evaluated under the study track because it meets the criteria of subrule (1)(a) of this rule, within 10 business days after the electric utility notifies the applicant that the interconnection application has been accepted pursuant to R 460.936, the electric utility shall provide to the applicant an individual study agreement or an agreement for an alternative process pursuant to R 460.956.
(3) If the interconnection application must be evaluated under the study track because it meets the criteria of subrule (1)(b), (c), or (d), of this rule, within 10 business days after the applicant has notified the electric utility to proceed to the study track, the electric utility shall provide to the applicant an individual study agreement or an agreement for an alternative process.
(4) An electric utility's interconnection procedures may include a provision for determining appropriate milestone payments to include with the system impact study fee and facilities study fee.