Section R. 460.922 - Online applications and electronic submission

Universal Citation: MI Admin Code R. 460.922

Current through Vol. 24-16, September 15, 2024

Rule 22.

(1) An electric utility shall allow pre-application report requests, interconnection applications, and interconnection agreements to be submitted electronically, such as, through the electric utility's website or via email.

(2) An electric utility shall dedicate a page on its website or direct customers to a linked website with information on these rules. The relevant information available to an applicant or interconnection customer via a website must include all of the following:

(a) These rules and interconnection procedures in an electronically searchable format.

(b) The electric utility's applications and all associated forms in a format that allows for electronic entry of data.

(c) Sample documents including, at a minimum, a 1-line diagram with required labels.

(d) Contact information for the electric utility's DER interconnection coordinator, including an email address and a phone number.

(e) Directions for the submission of applications.

Disclaimer: These regulations may not be the most recent version. Michigan may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.