Michigan Administrative Code
Department - Licensing and Regulatory Affairs
Public Service Commission
Interconnection and Distributed Generation Standards
Part 2 - INTERCONNECTION STANDARDS
Section R. 460.911 - Applicability
Universal Citation: MI Admin Code R. 460.911
Current through Vol. 24-16, September 15, 2024
Rule 11. These rules apply to all interconnection applications filed on or after the effective date of these rules. The electric utility shall complete work on any interconnection study agreement executed prior to the effective date of these rules, pursuant to the terms and conditions of that interconnection study agreement. Any new studies or other additional work must be completed pursuant to these rules. An electric utility or an alternative electric supplier shall not restrict access to interconnection for level 1, level 2, and level 3 DERs that are not participants in the legacy net metering or distributed generation programs.
Disclaimer: These regulations may not be the most recent version. Michigan may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.