Michigan Administrative Code
Department - Licensing and Regulatory Affairs
Public Service Commission
Interconnection and Distributed Generation Standards
Part 1 - GENERAL PROVISIONS
Section R. 460.908 - Timelines for electric utilities serving fewer than 1,000,000 in-state customers

Universal Citation: MI Admin Code R. 460.908
Current through Vol. 24-16, September 15, 2024

Rule 8. An electric utility serving fewer than 1,000,000 in-state customers shall have an additional 10 business days to comply with the timelines in R 460.911 to R 460.1026. This rule does not apply to applicants or interconnection customers.

Disclaimer: These regulations may not be the most recent version. Michigan may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.