Michigan Administrative Code
Department - Licensing and Regulatory Affairs
Bureau of Fire Services
Underground Storage Tank Regulations. R 29.2101-29.2192
AMENDMENTS TO ADOPTED FEDERAL REGULATIONS
Subpart K - UST SYSTEMS WITH FIELD-CONSTRUCTED TANKS AND AIRPORT HYDRANT FUEL DISTRIBUTION SYSTEMS
Section R. 29.2192 - Additions, exceptions, and alternatives for UST systems with field-constructed tanks and airport hydrant systems
Current through Vol. 24-16, September 15, 2024
Rule 92. Section 280.252 is added as adopted from the July 15, 2015, EPA-UST rules as follows:
Section 280.252. Additions, exceptions, and alternatives for UST systems with field-constructed tanks and airport hydrant systems.
(a) Exception to piping secondary containment requirements. Owners and operators may use single walled piping when installing or replacing piping associated with UST systems with field-constructed tanks greater than 50,000 gallons and piping associated with airport hydrant systems. Piping associated with UST systems with field-constructed tanks less than or equal to 50,000 gallons not part of an airport hydrant system shall meet the secondary containment requirement when installed or replaced.
(b) Upgrade requirements. Not later than October 13, 2018, airport hydrant systems and UST systems with field-constructed tanks where installation commenced on or before October 13, 2015 shall meet the following requirements or be permanently closed pursuant to subpart G of these rules.
(c) Walkthrough inspections. In addition to the walkthrough inspection requirements in section 280.36, owners and operators shall inspect the following additional areas for airport hydrant systems at least once every 30 days if confined space entry according to the Occupational Safety and Health Administration (see 29 CFR part 1910) is not required or at least annually if confined space entry is required and keep documentation of the inspection according to subsection 280.36(b).
(d) Release detection. Owners and operators of UST systems with field-constructed tanks and airport hydrant systems must begin meeting the release detection requirements described in this subpart not later than October 13, 2018.
MAXIMUM LEAK DETECTION RATE PER TEST SECTION VOLUME |
||
Test section volume (gallons) |
Semiannual test-leak Annual test-leak detection rate not to exceed detection rate not to exceed (gallons per hour) (gallons per hour) |
|
<50,000 |
1.0 |
0.5 |
[GREATER THAN EQUAL TO]50,000 to 75,000 |
1.5 |
0.75 |
[GREATER THAN EQUAL TO]75,000 to 100,000 |
2.0 |
1.0 |
[GREATER THAN EQUAL TO]100,000 |
3.0 |
1.5 |
PHASE IN FOR PIPINIG SEGMENTS [GREATER THAN EQUAL TO]100,000 GALLONS IN VOLUME |
|
First test |
Not later than October 13, 2018 (may use up to 6.0 gph leak rate). |
Second test |
Between October 13, 2018 and October 13, 2021 (may use up to 6.0 gph leak rate). |
Third test |
Between October 13, 2021 and October 13, 2022 (must use 3.0 gph for leak rate). |
Subseque nt tests |
After October 13, 2022, begin using semiannual or annual line testing according to the Maximum Leak Detection Rate Per Test Section Volume table above. |
(e) Applicability of closure requirements to previously closed UST systems. When directed by the implementing agency, the owner and operator of an UST system with field-constructed tanks or airport hydrant system permanently closed before October 13, 2015 shall assess the excavation zone and close the UST system in accordance with subpart G of these rules if releases from the UST may, in the judgment of the implementing agency, pose a current or potential threat to human health and the environment.