Rule 52. Sections 1.9, 1.9.1, 1.9.2, 1.9.3, 1.9.4, 1.9.5 and 1.9.6 of the LPG code are added as follows: 1.9 Permits.

1.9.1 An owner or owners designee shall submit an application for plan review to the bureau not less than 30 days before the installation of a LPG storage tank system of more than 2,000 gallon individual water capacity, more than 4,000 gallon aggregate water capacity, or any container filling location.

1.9.2 The installation application shall include a plot map that shows all of the following information:

(a) The locations of buildings, public roadways, railroad mainlines, and power lines.

(b) Storm sewers, sanitary sewers, manholes, and catch basins.

(c) The proposed locations of tanks and buildings.

(d) The location of property lines.

(e) The location of existing tanks, aboveground and underground, within 50 feet (15 meters) of the installation.

(f) The material of construction, the dimension, and the capacity of each tank.

(g) The manufacturer name and part number of all required container and piping appurtenances.

1.9.3 The bureau shall issue a plan review report within 30 days of the receipt. If the report is not issued within 30 days, the installation may be constructed according to the submitted plans and shall comply with these rules.

1.9.4 Upon completion of the installation, the owner or designee shall notify the bureau not fewer than 7 calendar days before the installation is placed in service. The bureau shall inspect the installation following the receipt of notification and shall certify the installation if the requirements of these rules have been met. If the inspection is not made within 7 calendar days of receipt of notification, the installation may be placed in service and a notarized affidavit shall be submitted to the bureau attesting to the fact that the installation complies with the plans submitted and applicable rules.

1.9.5 Upon request, all plans and specifications that are submitted to the bureau for review shall be returned after the bureau has certified the installation or within 30 working days after notification to the authority having jurisdiction of the completion of the installation. Plans and specifications may be marked "confidential do not copy" when they are submitted.

1.9.6 If construction of the storage system is not commenced within 1 year after date of approval, an installation application shall be resubmitted pursuant to this section. Fees required under the act shall be submitted with the resubmitted application.

Disclaimer: These regulations may not be the most recent version. Michigan may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.