Section R. 322.1016 - Inspection and certification of completed projects

Universal Citation: MI Admin Code R. 322.1016

Current through Vol. 24-04, March 15, 2024

Rule 16.

(1) The department may issue a certification for a project after final inspection, if the project was satisfactorily performed according to state permit.

(2) Where notice of certification is required as a permit condition, the permittee shall notify the department within 10 days of completion of the project to schedule a final inspection for certification. The department shall schedule its field inspection of a completed project when weather conditions will permit a thorough inspection.

(3) When any permit conditions are not complied with, enforcement action may be brought against the permit holder.

Disclaimer: These regulations may not be the most recent version. Michigan may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.