Rule 8. Pursuant to the provisions of section 35(1)(a) of the act, completion of a new, reconstructed, enlarged, repaired, or altered dam occurs when all the work depicted on all approved drawings and all specification requirements have been accomplished and all permit conditions have been implemented before the expiration of a permit.

Disclaimer: These regulations may not be the most recent version. Michigan may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.