Each Submission for a Permit (or component thereof) is subject to a deadline by which the DEC must make a decision i.e., take a final vote. Listed are the applicable time periods, measured from the date of the DOC. The time limits for Level One reviews may be extended by mutual written agreement of the Applicant and the Director. The time limits for Level Two reviews also may be extended by a written agreement of the Applicant and the DEC. In a Submission with more than one component, the longest time limit associated with one component shall apply to the entire Submission.

TABLE 3: TIME LIMITS FOR REVIEW

Time Limit in Days

Level One Review

Lotting Plan

14

Development Plan

21

Engineering Adjustment

14

Building or Occupancy Permit

30

Other reviews authorized in the By-laws, Article III, Section D

21

Level Two Review

(inclusive of the date of the DEC's vote)

Site Plan Review

75

Subdivision Approval

75

Wetlands

63

Variances

90

Reconsiderations (measured from the date of the request)

45

Historic District Certificates of Appropriateness

45

Disclaimer: These regulations may not be the most recent version. Massachusetts may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.