Title 945 CMR 3.00 - Notice To Proceed To Use Design Build For Public Works Construction Contracts Pursuant To MGL c. 149a, Sections 15 Through 21
Section 3.05 - Procedures
Current through Register 1531, September 27, 2024
(1) Establishment of Procedures. The Office of the Inspector General shall establish Procedures that specify the requirements and conditions that an awarding authority must meet to be issued a Notice to Proceed.
Content of Procedures. The Procedures shall include the standards as prescribed by the Inspector General that an awarding authority must meet to obtain a notice to proceed, the policies that the Office of the Inspector General will use in a review of the application to proceed, and the specific procedures that an awarding authority must follow to obtain a notice to proceed.
(2) General Information. The Procedures shall include general information on the design build delivery method of public construction.