Code of Massachusetts Regulations
945 CMR - OFFICE OF THE INSPECTOR GENERAL
Title 945 CMR 2.00 - Notice To Proceed To Use The Construction Manager At Risk Alternative Delivery Method For Public Building Construction Contracts Pursuant To MGL c. 149a, Sections 1 Through 11
Section 2.07 - Notice to Proceed

Universal Citation: 945 MA Code of Regs 945.2

Current through Register 1531, September 27, 2024

(1) Issuance of Notice to Proceed. The Inspector General shall issue a Notice to Proceed to use construction management at risk services to an awarding authority once the awarding authority has met the requirements as prescribed by the Inspector General. At a minimum, the awarding authority will be required to demonstrate that it has the authority and capacity to proceed; that it has a plan and procedures to effectively procure and manage the project; that it has retained a qualified owner's project manager; that it has retained a qualified designer; and, that it has procedures to ensure fairness in competition, evaluation, selection, and reporting.

(2) After receiving a notice to proceed, an awarding authority may use the construction management at risk delivery method. The awarding authority shall procure a construction management at risk firm in a manner consistent with M.G.L. c. 149A, § 5 through 11 and 945 CMR 2.00.

Disclaimer: These regulations may not be the most recent version. Massachusetts may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.